Question
Assume that ABC Company has invested a budget of 36 million riyals for XY project and planned to complete in 12 months. Lets also assume
Assume that ABC Company has invested a budget of 36 million riyals for XY project and planned to complete in 12 months. Lets also assume that the company planned to spend the budget equally in each month. However, when the first two months has passed, the project manager has found out that the total of two million riyals spent.
Based on the above scenario, answer the following:
Suppose RP=0.25
a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b) How much will it actually cost the company to complete this project, and how long will it really take to complete it based on the performance to date?
c) What do o you think of the project performance? over/under the budget? behind /ahead the schedule? Justify your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started