Assume that GIG Company has contracted to build an office building for Middle Company for $4,800,000. Middle Company has title to the office building during
Assume that GIG Company has contracted to build an office building for Middle Company for $4,800,000. Middle Company has title to the office building during the entire construction period. The construction costs were estimated initially to be $3,680,000. Other relevant data is as follows:
| 2017 | 2018 | 2019 |
|
|
|
|
|
|
Current period costs | $1,472,000 | $1,856,000 | $820,000 |
|
Estimated additional costs to complete | 2,208,000 | 832,000 | 0 |
|
Progress billings | 1,000,000 | 1,500,000 | 2,300,000 |
|
Collection on billings-current year | 725,000 | 1,000,000 | 3,075,000 |
|
Additional information:
- Contract price remained unchanged throughout the construction
Required:
- Calculate the revenues to be recognized for the years 2017 and 2018 assuming GIG Company uses the percentage of completion method. Calculate the percentage, complete rounding to the nearest whole percent. (4 marks)
- Prepare journal entries for GIG Company for 2017 using the percentage of completion method. (9 marks)
| 2017 | 2018 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
General Journal | |||
Date | Account Titles and Explanation | Debit | Credit |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Help ASAP!!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started