Assume that Harrisburg completed the office and warehouse building on December 31, 2014, as planned at a total cost of $5,211,500, and the weighted average
Assume that Harrisburg completed the office and warehouse building on December 31, 2014, as planned at a total cost of $5,211,500, and the weighted average amount of accumulated expenditures was $3,816,600. Compute the avoidable interest on this project.