Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Assume that Pearle Vision uses standard costs to control the materials in its made - to - order sunglasses. The standards call for 2 ounces
Assume that Pearle Vision uses standard costs to control the materials in its madetoorder sunglasses. The standards call for ounces of material for each pair of lenses. The standard cost per ounce of material is $ During July, the Santa Clara location produced pairs of sunglasses and used ounces of materials. The cost of the materials during July was $ per ounce, and there were no beginning or ending inventories.
Required
a Determine the flexible budget materials cost for the completion of the pairs of glasses.
$Answer
b Determine the actual materials cost incurred for the completion of the pairs of glasses and compute the total materials variance.
$Answer
actual materials cost
$Answer
Answer
F
total materials variance
c How much of the total variance was related to the price paid to purchase the materials?
$Answer
Answer
U
d How much of the difference between the answers to requirements a and b was related to the quantity of materials used? Hint: Compute materials quantity variance.
$Answer
Answer
F
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started