Assume that Product Z is made of three units of A and four units of B. A is made of three units of C and
Assume that Product Z is made of three units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units are required in Period 10 (Assume that there is currently no inventory on hand of any of these items.) a) Show the bill of materials (product structure tree). b) Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.
1 2 3 4 5 6 7 8 9 10 Item: Z Onhand: 0 LT: 2 SS: Q: L4L Item: A Onhand: 0 LT: 1 SS: Q: L4L Item: B Onhand: 0 LT: 1 SS: Q: L4L Period: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item: C Onhand: 0 LT: 1 SS: Q: L4L Item: D Onhand: 0 LT: 1 SS: Q: L4L Item: E Onhand: 0 LT: 3 SS: Q: L4LStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started