Assume that Product Z is made of two units of A and three units of B . A is made of three units of C
Assume that Product Z is made of two units of A and three units of B A is made of three units of C and four of D D is made of two units of E
Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A B C and D take one week each; and E takes three weeks.
Sixty three units OF Product Z are required in Period Assume that there is currently no inventory on hand of any of these items.
b Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. Leave no cells blank be certain to enter wherever required.
Period
Gross requirements
Item Z
Scheduled receipts
OH
Projected available balance
LT
Net requirements
SS
Planned order receipts
Q LL
Planned order releases
Gross requirements
Item A
Scheduled receipts
OH
Projected available balance
LT
Net requirements
SS
Planned order receipts
Q LL
Planned order releases
Gross requirements
Item B
Scheduled receipts
OH
Projected available balance
LT
Net requirements
SS
Planned order receipts
Q LL
Planned order releases
Gross requirements
Item C
Scheduled receipts
OH
Projected available balance
LT
Net requirements
SS
Planned order receipts
Q LL
Planned order releases
Gross requirements
Item D
Scheduled receipts
OH
Projected available balance
LT
Net requirements
SS
Planned order receipts
Q LL
Planned order releases
Gross requirements
Item E
Scheduled receipts
OH
Projected available balance
LT
Net requirements
SS
Planned order receipts
Q LL
Planned order releases
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started