Assume that Richard Wilson has reviewed his work schedule and decided that it makes sense to complete this project on time. Assuming that he now

Assume that Richard Wilson has reviewed his work schedule and decided that it makes sense to complete this project on time. Assuming that he now believes that the probability for completing the project on time is 92% and otherwise it will be finished 1 week late, determine the transaction price.