Assume that the chart below shows the probability (on the vertical y-axis) that a project will complete within X days (X on the horizontal x-axis).
Assume that the chart below shows the probability (on the vertical y-axis) that a project will complete within X days (X on the horizontal x-axis). Is the following statement true or false: there is a better than 50% chance that the project will complete between 12 and 20 days