Assume that the following tasks are performed on an assembly line with 8 hour workdays and average daily demand of 8 0 0 units per
Assume that the following tasks are performed on an assembly line with hour workdays and average daily demand of units per day. Begin by mapping out the process.
Answer the following questions:
A What cycle time is required to meet demand?
B Theoretically, how many stations are required to achieve this cycle time?
C Balance the assembly line assuming stations and using the longestoperating time rule, compute station time and idle time for each station.
D What is the efficiency of this line assuming that the cycle time is what you calculated for A
E Suppose demand increases to unitsday what's the new required cycle time and which stations need to be rebalanced if any?
A
B
C
Station
Tasks
D
E
Station Time
Station Idle Time
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started