Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Assume that the standard cost to make one finished unit includes 2 hour of direct labor at $4 per hour. During March, 12,000 direct labor-hours
Assume that the standard cost to make one finished unit includes 2 hour of direct labor at $4 per hour. During March, 12,000 direct labor-hours were worked, 5,250 units of product were manufactured, and total direct labor cost was $60,000. What is the labor rate variance for March?
Group of answer choices
$4,000 (U)
$12,000 (F)
$12,000 (U)
$4,000 (F)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started