Assume that you are the project manager for the construction of a 15-km road. Further assume that the work is uniformly distributed over 12 weeks.
Assume that you are the project manager for the construction of a 15-km road. Further assume that the work is uniformly distributed over 12 weeks. The total approved budget for this project is $600,000. At the end of the first three weeks of work, 160,000 AED has been spent, and five km of road have been completed. What is the schedule variance?