Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Assume that you have completed three months of the project. The BAC was $200,000 for this six-month project. You can also make the following assumptions:

Assume that you have completed three months of the project. The BAC was $200,000 for this six-month project. You can also make the following assumptions:

PV = 120,000

EV = 100,000

AC = 90,000 .

a)What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

b)How is the project doing? Is it ahead of schedule or behind schedule? Is it under budge or over budget?

c)Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

d)Use the SPI to estimate how long it will take to finish this project.

e)Sketch an earned value chart using the preceding information. See bellow figure as a guideline.


An EAC Estimate at completion (EAC) point above and to the right of the BC point means the project is projected to cost more and take 120,000 Budget at completion (BAC 100,000 80,000- Planned value (PV) $ 60,000 Actual cost (A9 longer than planned 40,000 Earned value (EV) 20,000 i2 3 4 56 7 8 9 10 11 12 13 Month .... Actual cost (AC) - Planned value (PV) Earned value (EV)

Step by Step Solution

3.49 Rating (169 Votes )

There are 3 Steps involved in it

Step: 1

Negative SV Shows thet it took mote time then planned to Sdluti... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Networking A Top-Down Approach

Authors: James F. Kurose, Keith W. Ross

5th edition

136079679, 978-0136079675

More Books

Students also viewed these Computer Network questions

Question

What are the different techniques used in decision making?

Answered: 1 week ago

Question

Maintain five-figure accuracy

Answered: 1 week ago

Question

Maintain five-figure accuracy

Answered: 1 week ago