Question
Assume that you have completed three months of the project. The BAC was $200,000 for this six-month project. You can also make the following assumptions:
Assume that you have completed three months of the project. The BAC was $200,000 for this six-month project. You can also make the following assumptions:
PV = 120,000
EV = 100,000
AC = 90,000 .
a)What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b)How is the project doing? Is it ahead of schedule or behind schedule? Is it under budge or over budget?
c)Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d)Use the SPI to estimate how long it will take to finish this project.
e)Sketch an earned value chart using the preceding information. See bellow figure as a guideline.
An EAC Estimate at completion (EAC) point above and to the right of the BC point means the project is projected to cost more and take 120,000 Budget at completion (BAC 100,000 80,000- Planned value (PV) $ 60,000 Actual cost (A9 longer than planned 40,000 Earned value (EV) 20,000 i2 3 4 56 7 8 9 10 11 12 13 Month .... Actual cost (AC) - Planned value (PV) Earned value (EV)
Step by Step Solution
3.49 Rating (169 Votes )
There are 3 Steps involved in it
Step: 1
Negative SV Shows thet it took mote time then planned to Sdluti...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started