Assume the following activity times: Activity Time (week) A 5 B 1 C 4 D 2 E
Fantastic news! We've Found the answer you've been seeking!
Question:
Assume the following activity times:
Activity | Time (week) |
A | 5 |
B | 1 |
C | 4 |
D | 2 |
E | 7 |
F | 1 |
G | 3 |
H | 8 |
I | 5 |
J | 3 |
K | 4 |
L | 5 |
M | 1 |
N | 1 |
O | 4 |
P | 3 |
Q | 3 |
R | 2 |
S | 3 |
T | 2 |
A) Develop a Gantt chart assuming the project starts on the last Monday of April. Assume that no work is performed on weekends.
B) Determine the ED and EF times, the LS and LF times, and slack for each activity.
C) Indicate the critical path and project duration.