Assume the job cost sheet for Job X shows that (1) it used 18 direct labor-hours and incurred direct materials and direct labor charges of
Assume the job cost sheet for Job X shows that (1) it used 18 direct labor-hours and incurred direct materials and direct labor charges of $500 and $360, and (2) its unit product cost is $27.35. If Job X contained 40 units, then what is the plantwide predetermined overhead rate per direct labor-hour?