Assume you are risk-averse and have the following three choices. Expected Value Project Standard Deviation A B C $ 2,050 2,750 2,120 $ 1,430
Assume you are risk-averse and have the following three choices. Expected Value Project Standard Deviation A B C $ 2,050 2,750 2,120 $ 1,430 1,130 1,260 a. Compute the coefficient of variation for each. Note: Round your answers to 3 decimal places. Coefficient of Project Variation A B C