Question

1 Approved Answer

Assume you are the project manager and based on your customer s requirements you have determined there are four main tasks in a Dream Backyard

Assume you are the project manager and based on your customers requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1- $50,000); all plumbing, electrical, and mechanical installed (Task 2- $20,000); a pool deck with planters and a raised fire pit (Task 3- $15,000); and landscaping and clean up (Task 4- $5,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows:
Budgeted Per Week (in 000s)
TBC 12345
Task 1501520105
Task 22061112
Task 315942
Task 4523
What is the total cumulative TBC? What is TBC at the end of week 4?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management

Authors: Andrew J DuBrin

10th Edition

0996757872, 9780996757874

More Books

Students also viewed these General Management questions

Question

3. Avoid making mistakes when reaching our goals

Answered: 1 week ago