Question
Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the project. Your
Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the project. Your company's database indicates that developers can handle eight function points each person-month and that the cost per developer at your firm is $5,800 per month. You and your team of five developers have come up with the following requirements: (Round your "Estimated duration" answer to 2 decimal places.)
Elements | Count | Complexity | ||
Inputs | 14 | Low | ||
Outputs | 8 | Low | ||
Inquiries | 8 | High | ||
Files | 32 | Medium | ||
Interfaces | 22 | High |
Calculate the total number of function points and the estimated cost and duration of the Tidal project? (Use "complexity weighting").
- Estimated total number of function points.
- Estimated cost.
- Estimated duration.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started