Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the project. Your

Assume you are the project manager for the Tidal 2 software project. You have been
asked to calculate the expected cost for the project. Your companys database indicates
page 161
that developers can handle eight function points each person-month and that the cost
per developer at your firm is $5,000 per month. You and your team of five developers
have come up with the following requirements:
Elements Count Complexity
Inputs 10 Low
Outputs 4 Low
Inquiries 4 High
Files 28 Medium
Interfaces 18 High
Using the complexity weighting scheme shown in Table 5.2 and the information
provided, calculate the total number of function points, the estimated cost, and the
estimated duration of the Tidal 2 project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Management With Website Development Applications

Authors: Greg Riccardi

1st Edition

0201743876, 978-0201743876

More Books

Students also viewed these Databases questions

Question

3. Is it a topic that your audience will find worthwhile?

Answered: 1 week ago

Question

2. Does the topic meet the criteria specified in the assignment?

Answered: 1 week ago