Assume you have planned for a project and have 2 0 activities all connected to each -
Fantastic news! We've Found the answer you've been seeking!
Question:
Assume you have planned for a project and have activities all connected to eachother FSback to back As per your estimation, the first activities would cost $ each, and the remaining ones would cost $ each. Then you go to the executing phase and as of today, your schedule says that you would be done with percent of the activities by today. While collecting the status updates from the team members, you found out that the first components were completed at a cost of $ Assuming the reason for variations in cost until now, will be repeated in future, what will be your EaC for project