Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a

  1. Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark)

    COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost is GHS0.60 per order and the holiday cost is 10% per annum.

    Required:

  2. Calculate
  3. The economic order quantity. (1.5 marks)
  4. The number of orders required per year. (1 mark)
  5. The total cost of ordering and holding the components for the year. (1 mark)
  6. Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark)

    COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost is GHS0.60 per order and the holiday cost is 10% per annum.

    Required:

  7. Calculate
  8. The economic order quantity. (1.5 marks)
  9. The number of orders required per year. (1 mark)
  10. The total cost of ordering and holding the components for the year. (1 mark)
  11. Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark)

    COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost is GHS0.60 per order and the holiday cost is 10% per annum.

    Required:

  12. Calculate
  13. The economic order quantity. (1.5 marks)
  14. The number of orders required per year. (1 mark)
  15. The total cost of ordering and holding the components for the year. (1 mark)
  16. Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark)

    COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost is GHS0.60 per order and the holiday cost is 10% per annum.

    Required:

  17. Calculate
  18. The economic order quantity. (1.5 marks)
  19. The number of orders required per year. (1 mark)
  20. The total cost of ordering and holding the components for the year. (1 mark)
  21. Assuming that there is no safety stock and that the present stock level is 400 components, when should the next order be placed? (Assume a 360-day year.) (1 mark)

    COVID-19 Ltd produces a specialized product; LOCKDOWN which has a constant monthly demand of 4000 units. The LOCKDOWN requires a component which COVID-19 Ltd purchases from a supplier at GHS10 per unit. The component requires a three-day lead time from the date of order to the date of delivery. The ordering cost is GHS0.60 per order and the holiday cost is 10% per annum.

    Required:

  22. Calculate
  23. The economic order quantity.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions