Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To

At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days).

Immediate Most
Activity Predecessor(s) Optimistic Probable Pessimistic
A: Negotiate contract with - 10 11 15
selected musicians
B: Reserve site - 7 9 11
C: Manage travel logistics A 5 7 12
for music group
D: Screen & hire B 3 4 5
security personnel
E: Arrange advertising C 6 6 6
& ticketing
F: Hire parking staff A, D 6 8 10
G: Arrange concession sales E 3 9 12

  1. Which project network is correct?
(i) (ii)
(iii) (iv)
  1. Compute the expected duration and variance of each activity. If required, round your answer to two decimals. If your answer is zero, enter 0.
Activity Expected Time Variance
A fill in the blank 2 fill in the blank 3
B fill in the blank 4 fill in the blank 5
C fill in the blank 6 fill in the blank 7
D fill in the blank 8 fill in the blank 9
E fill in the blank 10 fill in the blank 11
F fill in the blank 12 fill in the blank 13
G fill in the blank 14 fill in the blank 15
Critical
Activity ES LS EF LF Slack Activity
A fill in the blank 16 fill in the blank 17 fill in the blank 18 fill in the blank 19 fill in the blank 20 YesNoYes
B fill in the blank 22 fill in the blank 23 fill in the blank 24 fill in the blank 25 fill in the blank 26 YesNoNo
C fill in the blank 28 fill in the blank 29 fill in the blank 30 fill in the blank 31 fill in the blank 32 YesNoYes
D fill in the blank 34 fill in the blank 35 fill in the blank 36 fill in the blank 37 fill in the blank 38 YesNoNo
E fill in the blank 40 fill in the blank 41 fill in the blank 42 fill in the blank 43 fill in the blank 44 YesNoYes
F fill in the blank 46 fill in the blank 47 fill in the blank 48 fill in the blank 49 fill in the blank 50 YesNoNo
G fill in the blank 52 fill in the blank 53 fill in the blank 54 fill in the blank 55 fill in the blank 56 YesNoYes
  1. Determine the critical path in the project network.
  2. What is the expected duration and variance of the critical path? If required, round your answer to two decimals. Expected duration = fill in the blank 59 Variance = fill in the blank 60
  3. What is the likelihood that the project will be completed within 30 days? If required, round your answer to four decimals. Note: Use Appendix B to identify the probability. Likelihood = fill in the blank 61
  4. If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration? If required, round your answer to one decimal place. A delay of 6 days to activity Baffect the time to complete this project because activity B has a slack of fill in the blank 63 days.

Using all paths through the project network, estimate the probability that the project will be completed within 30 days. Compare your answer to the answer in part e and explain. Round your answers for values to 2 decimal places and for probability values to 4 decimal places.

For path B-D-F:

fill in the blank 64

Cumulative probability fill in the blank 65

For path A-F:

fill in the blank 66

Cumulative probability fill in the blank 67

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management

Authors: Andrew J DuBrin

10th Edition

0996757872, 9780996757874

More Books

Students also viewed these General Management questions

Question

The relevance of the information to the interpreter

Answered: 1 week ago