At Nike Manufacturing the observed time is recorded to be 15 minutes for a job done by a worker whose rating is 80. The following
At Nike Manufacturing the observed time is recorded to be 15 minutes for a job done by a worker whose rating is 80. The following allowances are recommended by Management: 1.1 Personal Needs Allowances: 5% of Basic Time 1.2 Basic Fatigue Allowances: 2% of Basic Time 1.3 Contingency Work Allowances: 1% of Basic Time 1.4 Contingency delay Allowances 2% of Basic Time 1.5 Calculate the Basic Time, 1.6 Work Content and 1.7 Standard time for the Job.