At the beginning of 2017, the Mini Construction Company received a contract to build an office building for $1.2 million. Mini will construct the building
At the beginning of 2017, the Mini Construction Company received a contract to build an office building for $1.2 million. Mini will construct the building according to specifications provided by the buyer, and the project is estimated to take four years to complete. The cost breakdown is as follows. Determine the amount of revenue and gross profit to be recognized each year. (do not include $ in your answer, round to 4 decimal places).
2017 | 2018 | 2019 | 2020 | |
cost incurred during the year | 224,000 | 331,000 | 333,000 | 200,000 |
Estimated cost to complete | 800,000 | 555,000 | 222,000 | 0 |
2017 | 2018 | 2019 | 2020 | |
Revenue to be recognized in this period | ||||
Gross Profit |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started