Question
At the beginning of 2021 Carefree Contracting Corporation (CCC) enters into a contract to build a home for a customer that is expected to take
At the beginning of 2021 Carefree Contracting Corporation (CCC) enters into a contract to build a home for a customer that is expected to take three years to complete. The contract price is $4,000,000. Completion is scheduled for the end of 2023. CCC's year end is December 31.
| 2021 | 2022 | 2023 |
Actual costs incurred current year | $750,000 | $2,250,000 | $775,000 |
actual costs incurred prior years | -0- | 750,000 | 3,000,000 |
Cumulative actual costs incurred to date | 750,000 | 3,000,000 | 3,775,000 |
Estimated costs to complete end of year | 2,250,000 | 750,000 | -0- |
Total Costs | $3,000,000 | $3,750,000 | $3,775,000 |
Billings | $700,000 | $2,600,000 | $700,000 |
Cash Collections | 500,000 | 2,000,000 | 1,500,000 |
a. Compute the gross profit for 2021, 2022 and 2023 using the percentage-of-completion method.
b. Compute the gross profit for 2021, 2022 and 2023 using the zero gross profit method.
c. Prepare all necessary entries for 2021 assuming the use of the percentage-of-completion method.
d. Determine the net asset or net liability position for CCC at the end of 2021 and 2022 assuming that the percentage of completion method is used. e. Prepare the closing entry in 2023 under the percentage of completion method. f. Prepare the closing entries in 2023 under the zero gross profit method is used.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started