At the high level of activity in November, 6000 machine hours were run and power costs were $22000. In April, a month of low activity,
At the high level of activity in November, 6000 machine hours were run and power costs were $22000. In April, a month of low activity, 1000 machine hours were run and power costs amounted to $13000. Using the high-low method, the estimated fixed cost element of power costs is O $13000. O $10800. O $22000. O $11200