At times, Holiday takes on long term projects for theme parks. During 2016, Holiday took on 4-year, long term project for Christmas Land, a destination
At times, Holiday takes on long term projects for theme parks. During 2016, Holiday took on 4-year, long term project for Christmas Land, a destination theme park in Fargo, North Dakota. The total estimated cost of the project was $8,000,000 and the contract was for $9,850,000. The detail of the project to date is as follows: Note: the 2016 entries are already reflected in the 2016 trial balance but none of the 2017 entries have been recorded.
2016: Costs Incurred $3,500,000
Estimated Costs to Complete $6,500,000
Billings $2,800,000
Customer Receipts $1,980,000
2017: Costs Incurred $2,750,000
Estimated Costs to Complete $3,875,000
Billings $2,010,000
prepare appropriate analysis and journal entries
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started