At your first job out of college you have been assigned to the production of bottled soda. The process has upper and lower spec limits
At your first job out of college you have been assigned to the production of bottled soda. The process has upper and
lower spec limits of and respectively, with a mean of and standard deviation of Calculate
Cpk and then determine if the process is capable.
around your response to two decimal places
b Is the process capable?
A Yes, it is capable.
B No it is not capable.