ATTEMPT ALL THE QUESTIONS (4 ) As cost accountant of Rackets Ltd, you estimate the standard cost of making one unit is as follows: Direct
ATTEMPT ALL THE QUESTIONS
(4 ) As cost accountant of Rackets Ltd, you estimate the standard cost of making one unit is as follows:
Direct material 4 kilos at 7 per kilo
Direct wages 5 hours at 10 per hour
The actual cost of a batch of 1000 units was:
Direct material 28960 (4328 kilos)
Direct wages 50200 (5370 hours)
Calculate the following:
(vi) The total labour cost variance