Question
Average weekly demand is 800phones Standard deviation of weekly demand is 500phones Lot size (Q)is 2000 phones Now suppose that the lead time is reduced
Average weekly demand is 800phones Standard deviation of weekly demand is 500phones
Lot size (Q)is 2000 phones
Now suppose that the lead time is reduced to the average lead time of 2weeks but the standard deviation of lead timeis 1week
Samsung targets to deliver cell phones 2weeks after cell phones are ordered but cannot guarantee
(9-1) What should the safety inventory be if Walmart wishes to achieve CSL of 0.99?
(9-2) What should the safety inventory be if Walmart wishes to achieve frof 0.99?Now suppose Walmart, uses periodic review policy with review interval of 2weeks when lead time for the Samsung to replenish cell phones is 3weeksSamsung guarantees to deliver cell phones 3weeks after cell phones are ordered
(9-3) What should the safety inventory (ss) be if Walmart wishes to achieve CSL of 0.99?(9-4) What should OULbe if Walmart wishes to achieve CSL of 0.99?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started