Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support).

Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2011, Avery

budgets 2012 assembly-support costs to be $8,200,000 and 2012 direct labor-hours to be 205,000. At the end of 2012, Avery is comparing the costs of several jobs that were started and completed in 2012

Laguna Model

Mission Model

Construction period

Feb-June 2012

May-Oct 2012

Direct material costs

$106,570

$127,970

Direct labor costs

$36,580

$41,650

Direct labor-hours

910

1,070

Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2012 actual assembly-support costs were $8,525,000, and the actual direct labor-hours were 155,000.

REQUIRED:

1.

Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate. Why do they differ? Identify the formula to calculate the budgeted indirect cost rate and then calculate the rate.

Identify the formula to calculate the actual indirect cost rate and then calculate the rate.

2.

What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and (b) actual costing?

  1. Identify the formula to calculate the indirect costs under normal costing and then calculate the indirect costs for each model.
  2. Now calculate the total costs using normal costing for each model.
  3. Identify the formula to calculate the indirect costs under actual costing and then calculate the indirect costs for each model.
  4. Now calculate the total costs using actual costing for each model.

3.

Why might Avery Construction prefer normal costing over actual costing?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Karen Braun, Wendy Tietz, Louis Beaubien

4th Canadian Edition

013544344X, 9780135443446

More Books

Students also viewed these Accounting questions

Question

3 > O Actual direct-labour hours Standard direct-labour hours...

Answered: 1 week ago