Avila Academy: You have a $ 2 3 0 , 4 9 9 fixed - price contract for landscaping and new fencing with the owner

image text in transcribed
Avila Academy:
You have a $230,499 fixed-price contract for landscaping and new fencing with the owner of
You have bought $9,181 in fencing materials and have charged fencing work with $380 for
You have signed a $118,298 fixed-price subcontract for design and construction of
You have submitted a $38,558 progress payment bill to the owners.
Buchon Barn
You also have a $765,758 fixed-price contract for excavation and foundation construction
You have charged the excavation work with $185 hours @ $102/hr for use of a 430E
You have charged the foundation work with $1,136 for the use of a compressor and $36,773
You have submitted a $308,208 progress payment bill to the owners.
State the variances, costs and profit in excess of billings, billings in excess of costs and profit, and
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Statement Analysis and Security Valuation

Authors: Stephen Penman

5th edition

78025311, 978-0078025310

More Books

Students also viewed these Accounting questions

Question

Draw the cis and trans isomers of the compound 3-methyl-3-hexene.

Answered: 1 week ago

Question

Be able to explain the fi ve levels of maturity LO1

Answered: 1 week ago

Question

Know what process and practice maturity is all about LO1

Answered: 1 week ago