Avila Academy: You have a $ 2 3 0 , 4 9 9 fixed - price contract for landscaping and new fencing with the owner
Avila Academy:
You have a $ fixedprice contract for landscaping and new fencing with the owner of
You have bought $ in fencing materials and have charged fencing work with $ for
You have signed a $ fixedprice subcontract for design and construction of
You have submitted a $ progress payment bill to the owners.
Buchon Barn
You also have a $ fixedprice contract for excavation and foundation construction
You have charged the excavation work with $ hours @ $hr for use of a E
You have charged the foundation work with $ for the use of a compressor and $
You have submitted a $ progress payment bill to the owners.
State the variances, costs and profit in excess of billings, billings in excess of costs and profit, and
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started