Award 10.00 points EX9-2 Use the information contained below... Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost. Activity Crash cost Maximum ID (Slope) Crash Time Normal time Normal cost 150 100 100 50 200 D. 40 200 55 200 150 Total direct normal costs $1,000 6. 2 X 4. $1,000 Total cost: Completion time: 13 To compress from time period 13 to time 12 crash the following activity(s) (You may select more than one the question mark to produce a check mark for a correct answer and double click the box with the q a wrong anewer) To compress from time period 13 to time 12 crash the following activity(s) (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) 12 What is the adjusted total cost at time period 12? To compress from time period 12 to time 11 crash the following activity(s) (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) 12 What is the adjusted total cost at time period 11? To compress from time period 1 to time 10 crash the following activity(s) (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) 12 What is the adjusted total cost at time period 10? What is the crash point of the network? Time period weeks Total cost