Azalea Company began construction on a new office building on Jan. 1 of this year. The building was completed on Sept. 30. Expenditures were made
Azalea Company began construction on a new office building on Jan. 1 of this year. The building was completed on Sept. 30. Expenditures were made of $200,000 on Jan. 1; $300,000 on Sept. 1; and $300,000 on Dec. 31. The weighted average accumulated expenditures are:
Group of answer choices
$500,000
$300,000
$350,000