Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

B 67 Determining the status of the project shown - find the individual activity CV, CPI, SV, A8 2 and SPI. Then find the overall

image text in transcribed
image text in transcribed
B 67 Determining the status of the project shown - find the individual activity CV, CPI, SV, A8 2 and SPI. Then find the overall project CV, D 2 E 12 CPI, SV, SPI, BAC, PSD, EAC and SAC. Summarize the overall budget and schedule (current and forecasted finish) C ?119 6 K 1 Assume it is just after 9 weeks into this project, and data shown is current and correct (now update the times of the G69 J 5 activities as shown in the variances). H 11 # = Planned Time (Weeks) # = Time (Weeks) Used Just After 9 Weeks Into The Project TASK PV EV AC CV CPI SV Time SPI Variance A 5,250 5,250 6,850 1 week 0,125 9,125 8,725 7 v/ -1 week 7 C (P) 87.270* 43.635. 44.945-24 weeks D(N) 10.900 - PE(N) 177,200 - F (N) 92 400 G (P 18,2208 9.110* * 9.1 10- -. -3 weeks H(N) 42.020 - - - J(N) 17.500 KIN) 14,950 Totals -3 weeks 2 Currently BAC= (to date) Legend: - Initial Critical Path * - Task Incomplete, PV is 50% * * - Using 50-50 Rule * * * - Actual Cost To Date P- Task in Progress N - Task not Started PV - Planned Value EV - Earned Value AC - Actual Cost PSD - Planned Schedule Duration CV - Cost Variance SV - Schedule Variance CPI - Cost Performance Index SPI - Schedule Performance Index SAC - Schedule At Completion & - PV Is Maximum Because Task Was Scheduled To Be Complete

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept To Operation

Authors: John R Walker

5th Edition

0471740578, 9780471740575

More Books

Students also viewed these General Management questions

Question

Ctarltan romnons a. $23,020 b. $29,359 C. $8,351 d. $9,121

Answered: 1 week ago