( B ) A small project consists of seven activities with the following details. table [ [ Activity , DURATION, WEEKS, table [

(B) A small project consists of seven activities with the following details.
\table[[Activity,DURATION, WEEKS,\table[[Immediate],[Predecessor]]],[\table[[Most],[likely]],Optimistic,Pessimistic],[A,4,2,8,A],[B,7,3,15,A],[C,4,4,23,B, C],[D,11,5,16,B],[E,8,4,15,D, E],[F,6,3,5,D],[G,5,5,,]]
(i) Draw Network Diagram, find critical path, the expected completion time.
(ii) What project duration will have 95% confidence of completion? Take Z=1.64.10
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Social Media Measurement And Management

Authors: Jeremy Harris Lipschultz

1st Edition

0815363923, 978-0815363927

More Books

Students also viewed these General Management questions

Question

=+3. Who are the brand's competitors?

Answered: 1 week ago

Question

11.7 Discuss competency-based pay.

Answered: 1 week ago