Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

B show all your calculation Activity Description Immediate Time(Week) predecessors A Select site office 3 B Create a plan 5 C Determine personnel B 3

B show all your calculation

image text in transcribed
Activity Description Immediate Time(Week) predecessors A Select site office 3 B Create a plan 5 C Determine personnel B 3 requirements D Design facility A, C 4 E Construct interior D 8 F Select personnel C IN G Hire new employees F 4 H Move key personnel F 2 Financial arrangement B UT J Train personnel H, E,G 3 1) Construct the network diagram using either activity on node or activity on arrow. 2) Calculate early start, early finish, late start, and late finish for all activities. 3) What are the critical activities, Indicate the critical path and its duration on the diagram. 4) Calculate total float and free float of all activities

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Product Marketing Management

Authors: Suat Ozsoy

1st Edition

9798481471693

More Books

Students also viewed these General Management questions

Question

3. Where is the job to be accomplished?

Answered: 1 week ago