Using the below Program Evaluation and Review Technique (PERT) activity table, calculate the expected value and variance of each activity and state and interpret the

Using the below Program Evaluation and Review Technique (PERT) activity table, calculate the expected value and variance of each activity and state and interpret the standard deviation of the overall project.

*PLEASE SHOW ALL CALCULATIONS*

Activity

Predecessors

Optimistic (a)

Most Likely (m)

Pessimistic (b)

A

-

2

3

4

B

-

3

4

5

C

B

3

5

6

D

A

2

2

2

E

D

1

4

5

F

D

2

3

4

G

C,F

1

3

5

H

E,G

3

5

6

Step by Step Solution

3.38 Rating (148 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability And Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson

13th Edition

0135173620, 978-0135173626

More Books

Students also viewed these Accounting questions

Question

How much is 1/2 % of $10?

Answered: 1 week ago

Question

1301/2 % of $455 is what amount?

Answered: 1 week ago