b) What is the probability that activity F alone will take between 44 and 46 days? The following project has three independent paths as shown
b) What is the probability that activity F alone will take between 44 and 46 days? The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Optimistic $25; Pessimistic Expected Variance Activity Time Time Time (days) (days) (dBVSl A 10 16 23 -- i i i 3 20 23 42 -- c 13 30 42 -- o 15 1s 15 -- a) What is the probability that this project will be delayed