b) Where you have a potential delay of $100,000 per week, calculate the final cost in liquidated damages after 3 months (i.e. 12 weeks period),
b) Where you have a potential delay of $100,000 per week, calculate the final cost in liquidated damages after 3 months (i.e. 12 weeks period), particularly where the contractor was ordered to accelerate the works at a cost of $57,000 per week