Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

BA 476 Project Management Week 9 Assignment Crashing a Project Complete the worksheets below to calculate the total costs for each duration of the project.

BA 476 Project Management

Week 9 Assignment Crashing a Project

Complete the worksheets below to calculate the total costs for each duration of the project. In each worksheet:

Fill in the values in all boxes, including the letter x where appropriate

Respond everywhere you see an underscore (the cost questions and the question at the end)

Highlight the box(es) for the activities that you crashed

Add emphasis to arrows to show the critical path(s) (see example and note in the first worksheet below).

I need help, learning how to figure out my arrows and how to compute the total direct costs and total project costs. Also, how to figure out my critical path.

Thank you

image text in transcribedimage text in transcribedimage text in transcribed

Calibri (Body) - 14 - A A A E BIUXX A-Y.A. EEE E E . 2 1 1 . . AaBbCcDc AaBbCcDc AaBbc 1 Normal T No Spac. Heading 1 Paragraph Font Week 9 Assignment -crasning a Project Complete the worksheets below to calculate the total costs for each duration of the project. In each worksheet: Fill in the values in all boxes, including the letter x where appropriate Respond everywhere you see an underscore (the cost questions and the question at the end) Highlight the box(es) for the activities that you crashed Add emphasis to arrows to show the critical path(s) (see example and note in the first worksheet below). Activity Crash cost (slope) Max crash time Normal time Normal cost A 20 2 5 60 B403440 C00630 D10 12 10 E 901 6 100 F 502 20 G 402 60 30 1 40 I 100 110 Total: 470 Project duration: 17 time units (indirect costs, $2000) with the exception of the costs, we completed this first worksheet for you. This worksheet shows the normal times, did not highlight any of the boxes. Total direct cost for this duration: Total project cost for this duration: To add emphasis to the arrows on the critical path (as shown in the worksheet above): 1. Click on the arrow to select it (or use Ctrl+Click to select multiple arrows) 2. Click the format tab on the ribbon 3. Click the Shape Outline dropdown arrow 4. Point to Weight, and click the 3 pt option 5. Repeat for all arrows on the critical path(s) Steps might vary slightly in different versions of Microsoft Word BIU - x, x' A Paragraph Project duration: 14 time units (indirect costs, $1500) Total direct cost for this duration Total project cost for this duration: Project duration: 13 time units (indirect costs, $1300) Total direct cost for this duration Total project cost for the duration ga Project (3) - Word ab AaBb C ABECEDI AaBbc ABCD AaBbcc ABCDi AalbCD! AABUCCDC ABCD Aabcc de Subtitle Subtle Em.. Emphasis intense. Strong Quote Intense ... Subtle Rel... Intense Re. Book Title Project duration: 12 time units (indirect costs, $1250) Total direct cost for this duration: Total project cost for this duration: No need to crash beyond this point. Just respond to the following question: What is the optimum cost-time point for the project (.e. the duration that produces the lowest overall cost)? Provide the number of time units and the total project costs for that time unit. Calibri (Body) - 14 - A A A E BIUXX A-Y.A. EEE E E . 2 1 1 . . AaBbCcDc AaBbCcDc AaBbc 1 Normal T No Spac. Heading 1 Paragraph Font Week 9 Assignment -crasning a Project Complete the worksheets below to calculate the total costs for each duration of the project. In each worksheet: Fill in the values in all boxes, including the letter x where appropriate Respond everywhere you see an underscore (the cost questions and the question at the end) Highlight the box(es) for the activities that you crashed Add emphasis to arrows to show the critical path(s) (see example and note in the first worksheet below). Activity Crash cost (slope) Max crash time Normal time Normal cost A 20 2 5 60 B403440 C00630 D10 12 10 E 901 6 100 F 502 20 G 402 60 30 1 40 I 100 110 Total: 470 Project duration: 17 time units (indirect costs, $2000) with the exception of the costs, we completed this first worksheet for you. This worksheet shows the normal times, did not highlight any of the boxes. Total direct cost for this duration: Total project cost for this duration: To add emphasis to the arrows on the critical path (as shown in the worksheet above): 1. Click on the arrow to select it (or use Ctrl+Click to select multiple arrows) 2. Click the format tab on the ribbon 3. Click the Shape Outline dropdown arrow 4. Point to Weight, and click the 3 pt option 5. Repeat for all arrows on the critical path(s) Steps might vary slightly in different versions of Microsoft Word BIU - x, x' A Paragraph Project duration: 14 time units (indirect costs, $1500) Total direct cost for this duration Total project cost for this duration: Project duration: 13 time units (indirect costs, $1300) Total direct cost for this duration Total project cost for the duration ga Project (3) - Word ab AaBb C ABECEDI AaBbc ABCD AaBbcc ABCDi AalbCD! AABUCCDC ABCD Aabcc de Subtitle Subtle Em.. Emphasis intense. Strong Quote Intense ... Subtle Rel... Intense Re. Book Title Project duration: 12 time units (indirect costs, $1250) Total direct cost for this duration: Total project cost for this duration: No need to crash beyond this point. Just respond to the following question: What is the optimum cost-time point for the project (.e. the duration that produces the lowest overall cost)? Provide the number of time units and the total project costs for that time unit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions