Question
Balance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 45 pieces. Assume an 6-hour
Balance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 45 pieces. Assume an 6-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
Fill in the table below for a shift output of 60 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
Workstation | Tasks | Total Time | Idle Time |
1 | -Select-b, cc, fa, dItem 1 | ||
2 | -Select-a, eb, a, db, c, fItem 4 | ||
3 | -Select-d, f, g, ie, g, he, g, iItem 7 | ||
4 | -Select-h, j, ki, j, kj, kItem 10 | ||
Total |
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Fill in the table below for a shift output of 45 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
Workstation | Tasks | Total Time | Idle Time |
1 | -Select-b, a, da, b, cb, c, f, eItem 16 | ||
2 | -Select-e, c, g, fe, f, d, ga, d, g, iItem 19 | ||
3 | -Select-i, h, j, kh, j, ki, h, kItem 22 | ||
Total |
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started