Question
Barley Hopp, Inc., manufactures custom-ordered commemorative beer steins. Its standard cost information follows: Standard Quantity Standard Price (Rate) Standard Unit Cost Direct materials (clay) 1.80
Barley Hopp, Inc., manufactures custom-ordered commemorative beer steins. Its standard cost information follows:
Standard Quantity | Standard Price (Rate) | Standard Unit Cost | ||||||
Direct materials (clay) | 1.80 | lbs. | $ | 1.90 | per lb. | $ | 3.42 | |
Direct labor | 1.80 | hrs. | $ | 11.00 | per hr. | 19.80 | ||
Variable manufacturing overhead (based on direct labor hours) | 1.80 | hrs. | $ | 1.10 | per hr. | 1.98 | ||
Fixed manufacturing overhead ($396,000.00 180,000.00 units) | 2.20 | |||||||
Barley Hopp had the following actual results last year:
Number of units produced and sold | 185,000 | |
Number of pounds of clay used | 338,200 | |
Cost of clay | $ | 676,400 |
Number of labor hours worked | 230,000 | |
Direct labor cost | $ | 3,680,000 |
Variable overhead cost | $ | 360,000 |
Fixed overhead cost | $ | 380,000 |
Required: 1. Calculate the direct materials price, quantity, and total spending variances for Barley Hopp. (Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable and "U" for unfavorable.) 2. Calculate the direct labor rate, efficiency, and total spending variances for Barley Hopp. (Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable and "U" for unfavorable.) 3. Calculate the variable overhead rate, efficiency, and total spending variances for Barley Hopp. (Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable/Overapplied and "U" for unfavorable/underapplied.)
Barley Hopp, Inc., manufactures custom-ordered commemorative beer steins. Its standard cost information follows: Standard Standard Price Standard Quantity Rate Unit Cost Direct materials (clay) 1.80 lbs. S 90 per lb. 3.42 Direct labor 1.80 hrs. S 00 per hr. Variable manufacturing overhead (based on s 1.10 per hr direct labor hours 1.80 hrs. 9,80 1.98 Fixed manufacturing overhead ($396,000.00 2.20 180,000.00 units Barley Hopp had the following actual results last year: 185,000 Number of units produced and sold Number of pounds of clay used 338,200 Cost of clay 676.400 Number of labor hours worked 230,000 Direct labor cost $3,680,000 Variable overhead cost 360,000 3B0,000 Fixed overhead cost Required: 1. Calculate the direct materials price, quantity, and total spending variances for Barley Hopp. (Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable and "U" for unfavorable Answer is complete but not entirely correct 17,820X F X Direct Materials Price Variance Direct Materials Quantity Variance 21,200X U 3,300x u Direct Materials Spending Variance 2. Calculate the direct labor rate, efficiency, and total spending variances for Barley Hopp. (Do not round your intermediate calculations. Indicate the effect of each variance by selecting "F for favorable and "U" for unfavorable Answer is complete but not entirely correct 225,000X U Direct Labor Rate Variance 180,000XF Direct Labor Efficiency Variance U 45,000X Direct Labor Spending VarianceStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started