Based on the following table, we'd like to create AON network. What's the critical path? Activity Predecessor Duration (days) A 3 B A 4 C
Based on the following table, we'd like to create AON network. What's the critical path?
Activity | Predecessor | Duration (days) |
A | 3 | |
B | A | 4 |
C | A | 2 |
D | B | 5 |
E | C | 1 |
F | C | 2 |
G | D, E | 4 |
H | F, G | 3 |
a. | A->B->D->G->H | |
b. | A->C->E->G->H | |
c. | A->C->F->H | |
d. | A->B->E->G->H |