Question

1 Approved Answer

Based on the numerical information provided in the image, what is the expected output rate (per hour) of the process? What is the time per

Based on the numerical information provided in the image, what is the expected output rate (per hour) of the process? What is the time per stage, process and quantity per week and month? Assume a month is 4 weeks. Which part of the process flow image above is the bottleneck? Why?

 

Raw Materials Time - 100 hours Output - 1200 Manufacturing Time - 100 hours Output - 1600 Manufacturing Process Grinding Time - 100 hours Output - 800 Polishing Time 100 hours Output-1000 Packaging Time - 100 hours Output - 1600 Shipping Time - 100 hours Output - 2000 All time and outputs are per week

Step by Step Solution

3.54 Rating (158 Votes )

There are 3 Steps involved in it

Step: 1

1 Expected Output Rate per hour The expected output rate per hour can be calculated by summing up th... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these General Management questions

Question

How have these dividends related to earnings in these years?

Answered: 1 week ago

Question

Case : Karl and June Monroe

Answered: 1 week ago

Question

Determine miller indices of plane X z 2/3 90% a/3

Answered: 1 week ago