Question
Based on the project description which you have submitted as your project charter (individual assignment) answer the following questions: 1. Develop the work breakdown structure
Based on the project description which you have submitted as your project charter (individual assignment) answer the following questions: 1. Develop the work breakdown structure (including time, reseource allocation and any cost
allocation as required with no resource overallocation) (20 marks)
Develop procurement management plan (including current market analysis, identification and selection of suitable suppliers by using the selection matrix, selection of types of contract for each
supplier, risk assessment on each contract and prioritising these risks) (20 marks)
Develop a stakeholder communication management plan which identifies ten stakeholders, project info needs, stakeholder info needs, communication methods and timing to communicate
4.
with these stakeholders (only communication matrix)
(20 marks)
The figures used in Earned Value Analysis provide measures to indicate the status of a project incorporating measures for time, cost and scope. The key values are Earned Value, Planned Value
and Actual Cost.
The following calculations have been made for a project:
Budget at Completion (BAC) Time Estimate Earned Value (EV) Planned Value (PV)
Actual Cost (AC)
$290,000 12 months $65,000 $80,000 $79,000
a) b) c)
Calculate cost and schedule variances, cost and schedule performance indices, estimate to complete, estimate at completion and to complete performance index (5 marks) What do these figures (varirance, performance indices and estimates) indicate?
(10 marks)
If you are the Project Manager, what actions would you take based on these figures? (5 marks)
3. Consider the following network diagram for a project. The duration of each activity (in days) is given.
(a) Calculate early start, early finish, late start, and late finish for each of the activities using the
Two-Pass method. Assume the project starts on Day 0. Fill in the table below.
(6 marks)
Slack
Activity
A B C D E F G H
Early Start
Early Finish
Late Start
Late Finish
(b) Identify all of the paths on the network diagram and show their duration.
(c) What is the critical path for this project and how long is it?
(d) What does "slack" mean? Which of the activities in this project have slack?
(e) What would be the effect on the project if Activity E takes 10 days to complete?
(3 marks) (2 marks) (2 marks)
(2 marks) (f) As the project manager, what are the two techniques could you use to bring the project back to
its original scheduled completion target? Give an example using the data above to illustrate your
answer.
(5 marks)
C 7
End of Final Assessment
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started