Question
1 Approved Answer
Based on the table below, what is the PPC? A B C 507% 57% O 97%- 61% Work Hours EST ACT 14000 8940 1950 1246
Based on the table below, what is the PPC? A B C 507% 57% O 97%- 61% Work Hours EST ACT 14000 8940 1950 1246 800 356 FORECAST 15500 1960 510 Quantities EST ACT 1100 700 86 570 250 670 FORECAST 1100 195 680