Question

1 Approved Answer

Based on what you learned trom the scheduling lectures, which of the following statement about Bar Chart DAY / DATE Conversion is incorrect? Finish Times

Based on what you learned trom the scheduling lectures, which of the following statement about Bar Chart DAY/DATE Conversion is incorrect?
Finish Times -> BOTTOM
Early Times TOP
The start time of Day 1 is marked as 0
Start Times -> TOP (i.e., are marked at the top half of a calendar day cell)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions