basis for defining the project scope. One of the responsibilities of a project manager is to identify key project deliverables during this exercise. Where are
basis for defining the project scope. One of the responsibilities of a project manager is to identify key project deliverables during this exercise. Where are the key project deliverables documented?
A Scope Management Plan
B Requirement Management Plan
C Project Scope Statement
D Accepted Deliverables