Bauer Fabrications, Ltd., of Edinburg, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new

Bauer Fabrications, Ltd., of Edinburg, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months:

Month

1 2 3 4
Throughput time ? ? ? ?
Manufacturing cycle efficiency ? ? ? ?
Delivery cycle time ? ? ? ?
Percentage of on-time deliveries 81% 82% 87% 94%
Total sales (units) 11,810 11,990 11,930 11,820

Management would like to know the companys throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:

Month

1 2 3 4
Move time per unit, in days 0.6 0.8 0.6 0.4
Process time per unit, in days 0.6 0.9 0.8 0.7
Wait time per order before start of production, in days 11.8 10.1 7.1 6.1
Queue time per unit, in days 4.4 4.4 3.4 2.4
Inspection time per unit, in days 0.6 0.7 0.5 0.5

Required:
1a. Compute the throughput time for each month. (Round your answers to 1 decimal place.)
1 2 3 4
Throughput time in days

1b.

Compute the manufacturing cycle efficiency (MCE) for each month. (Do not round your intermediate calculations and round final answers to one decimal place (i.e., 0.123 should be entered as 12.3).)

1 2 3 4
Manufacturing cycle efficiency (MCE) % % % %

1c.

Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.)

1 2 3 4
Delivery cycle time in days

3. Refer to the move time, process time, and so forth, given for month 4.

a.

Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Do not round your intermediate calculations. Round your Throughput Time to 1 decimal place. Round your MCE percentage answer to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

Throughput time in days
Manufacturing cycle efficiency (MCE) %

b.

Assume that in month 6 the move time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Do not round your intermediate calculations. Round your Throughput Time to 1 decimal place. Round your MCE percentage answer to 1 decimal place (i.e., 0.123 should be entered as 12.3).)

Throughput time in days
Manufacturing cycle efficiency (MCE) %

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Top Accounting And Auditing Issues For 2023

Authors: CCH Tax Law Editors

1st Edition

0808059335, 978-0808059332

More Books

Students also viewed these Accounting questions

Question

Differentiate tan(7x+9x-2.5)

Answered: 1 week ago

Question

Explain the sources of recruitment.

Answered: 1 week ago

Question

Differentiate sin(5x+2)

Answered: 1 week ago

Question

Compute the derivative f(x)=1/ax+bx

Answered: 1 week ago