Question
BAY TURNS 25 25 years ago, Bay started out with a single promise to our customers quality. Unwavering from that pledge, our buildings are a
BAY TURNS 25
25 years ago, Bay started out with a single promise to our customers quality. Unwavering from that pledge, our buildings are a testament to the values of hard work, dedication, and entrepreneurial spirit all qualities central to our legacy. Each Bay project is a landmark, charting the course of our momentous 25-year journey. Behind the scenes are numerous notable milestones, all of which are outcomes of leadership and innovativeness. Such achievement is only possible when a team is fully dedicated to the goal of attaining all-around excellence.
Innovation has propelled Bay to progress and remain a leader. Focusing only on the high-end of the market challenged us to introduce novel ideas with each successive project so much so that, over five dozen of such amenities and features found in todays high-end Dhaka apartments are undisputedly Bays contribution, and many are now part of the National Building Code.
As Dhakas real estate market evolved, so did the customers demands. The moment Bay began to offer a one-stop solution, with complete interior fit-out customizable to the familys specific needs, it was a hit and the market followed suit. With the longstanding commitment to deliver durability and value, Bay also pioneered the advent of professional building maintenance and management.
BAY PROJECTS
Bays Chayaneer, Baridhara
Launch: May 2021 Completion: 2025
Total Apartments: 10
Snuggled in the heart of Baridhara, Chayaneer exudes a certain sophistication that sets it apart. Packed with all the features and amenities expected in a premium apartment and more, this can be your perfect retreat. Each floor is occupied by a single apartment, accessed from exclusive lobbies to ensure security and privacy.
Every part of this 3,600 sqft apartment has been meticulously planned using the highest quality materials, craftsmanship and interior design aesthetic.
Bays Lyra, Baridhara
Launch: June 2021 Completion: 2025
Total Apartments: 14
Bays Lyra stands testament to our unwavering commitment towards quality. Situated amidst the tranquil neighbourhood of Baridhara, this seamless blend of style and functionality is set to become the perfect home. Each floor is occupied by a single apartment, accessed from exclusive lobbies to ensure security and privacy. 4,500 sqft of clean, contemporary designer interiors, customized to meet the needs and wishes of each occupant complement the large patio gardens to bring a touch of elegance and nature into every unit.
Bays Seleste, Gulshan
Launch: July 2021
Completion: 2024
Total Apartments: 12 (equally distributed based on size)
Seleste is another of Bays projects situated in Gulshan. An amalgamation of contemporary design, nature, grandeur, customizable layouts tempered with the finest fittings and craftsmanship. All the sought-after hallmarks of a Bay project are on full display. Being located in the heart of Gulshan is yet another plus. The ground floor welcomes you with double height, professionally landscaped spaces with a water feature, and exclusive lift lobbies. Single apartment floors of 3,950 sqft and 4,150 sqft offer exclusivity and an exotic rooftop garden with an adjacent pool are just some of the amenities on offer.
Questions
- Conduct an online research and identify the fixed and variable costs related to construction. (2 marks)
- Now consider the following data related to selling price in each project
Bays Chayaneer: Tk 25000/ sqft
Bays Lyra: Tk 23000/ sqft
Bays Selste: Tk 22000/ sqft
For each of the projects determine the selling price by apartment type. (3 marks)
- The variable cost of building depends on the apartment sqft based on the following range
2000-2800 sqft= Tk 15,000/ sqft
2801- 3900 sqft= Tk 18,000/sqft
3901- 5000 sqft=Tk 20000/ sqft
Determine the break-even point for each project if the fixed costs are as follows
Site Electricity: Tk 60000/ project
Site Salary: Tk 95000/ project
Site Machinery: Tk 105000/ project
Site Common Costs: Tk 267000/ project.
Lift Installation: Tk 568000/ project
Gardening: Tk 273000/ project
Pool installation: Tk 134000/ project ( 2*3 =6 marks)
- One of the customers at Chayaneer and Lyra, decide to customize their apartment. While customizing, in both sites, he wants to install a food lift, some cabinets, and central air-conditioning. Costs related to the customization are given below
Food lift: Tk 42000/ lift/ site
Cabinets: Tk 24000/ cabinet/ site (Each site will have 3 cabinets each)
Central Air Conditioning: Tk 90000/site
Justify whether the customization should be allowed based on profitability analysis and qualitative justifications. ( 5 marks)
- At the end of March, based on overall business processes, the accounts department at BAY presented the following data to senior Management.
Summary:
Particular | Budget (m) | Actual (m) |
Cash inflow, sales and rental | 396 | 239 |
Cash outflow for expenses | 208 | 235 |
Excess / (Shortage) | 188 | 4 |
Using the above data and considering the following prepare a variance report giving detailed, possible explanations for the causes in variances in each category.
Consider the following
Cash inflow from Sales and Rentals
Cash outflow for Expenses (1.5*2 = 3 marks)
- The project management cell (PMC) is responsible for allocating cost and monitoring it over a project life cycle. How can the PMC department at Bay fulfil this process ensuring responsibility budgeting? (6 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance